Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
700 questions found · page 3 of 28
You are coaching a newly formed agile team that includes three junior developers and two senior developers. During the first two sprints, you notice the senior developers are completing most of the complex stories while junior developers are assigned only simple tasks. The senior developers say they are trying to help the team meet commitments, but the junior developers express frustration in private that they are not learning new skills. Sprint goals are being met, but you are concerned about long-term team capability and sustainability. What is the best approach?
September 29, 2026
Your agile team has two developers who consistently clash during daily standups and sprint planning. One developer prefers thoroughly discussing technical approaches before committing to work, while the other prefers to start coding quickly and iterate. Their disagreements are starting to affect team dynamics, with other team members avoiding engaging in technical discussions. Both developers are highly skilled and their work quality is excellent. Yesterday, their disagreement during refinement caused the session to run 30 minutes over time. What should you do?
September 29, 2026
During a sprint review, a key stakeholder becomes visibly upset when seeing the increment, stating that the features demonstrated are not what they expected, even though the stories were approved during sprint planning. The product owner defends the work, saying the team delivered exactly what was written in the user stories. The stakeholder insists the team must redo the work. Team morale drops immediately as they feel their hard work is being dismissed. How should you address this conflict?
September 29, 2026
Your agile development team includes members from four different countries across three time zones. During sprint planning, you notice that team members in the Asia-Pacific region rarely speak up, while team members in North America dominate the conversation. The sprint retrospectives show similar patterns. The team's velocity has been declining over the past two sprints, and some stories are being carried over because requirements were misunderstood. What is the most effective action to improve team collaboration?
September 29, 2026
You are leading an agile project team that has been working together for three sprints. During the latest retrospective, several team members express frustration that decisions are often delayed because they feel they need to wait for your approval on minor implementation details. The team has strong technical skills and has consistently met their sprint commitments. Team velocity is stable, but you notice team members seem hesitant to self-organize. What should you do to address this situation?
September 29, 2026
You are leading a regulatory compliance project using a hybrid approach where legal reviews follow predictive gates and process implementation uses iterative delivery. A new compliance regulation is announced mid-project that significantly impacts scope. The legal team insists on a complete requirements freeze and full impact analysis before proceeding (6-8 weeks), following their standard risk management protocol. The implementation team wants to continue iterating on unaffected areas and adapt as legal analysis progresses. The compliance deadline is regulatory-mandated and cannot move. Both teams believe their approach protects the organization, and tension is escalating. Several implementation team members have complained that legal is 'blocking progress,' while legal counsel has expressed concerns about 'reckless iteration' on compliance matters. What is your BEST course of action?
September 29, 2026
Your hybrid project includes an offshore agile development team and an onshore predictive implementation team. The agile team's Scrum Master has been highly effective, and team members openly share impediments and collaborate well. However, you've noticed in the predictive workstream that team members rarely speak up in status meetings, several risks weren't reported until they became issues, and there's high reliance on formal change control processes even for minor decisions. The predictive team lead is experienced but tends to make decisions unilaterally. Cultural assessments show the offshore team comes from a high power-distance culture while the predictive team reflects the corporate risk-averse culture. What should you do to create greater psychological safety across both workstreams?
September 29, 2026
You are managing a product development initiative using a hybrid approach where hardware follows a stage-gate predictive model and software uses Scrum. During integration testing, a critical hardware defect is discovered that requires three months to redesign and remanufacture—extending beyond the current software release schedule. The software team has already completed features dependent on the hardware specifications and wants to continue with new features. The hardware team is demoralized by the setback and feeling blamed. Senior management is pressuring you to maintain the original launch date. How should you lead the teams through this challenge?
September 29, 2026
Your organization is piloting agile practices within traditionally predictive portfolios. You're leading a hybrid project with a co-located agile team and distributed predictive workstreams across three continents. After four months, you notice the agile team has strong cohesion and high performance, but the distributed predictive teams report feeling disconnected and undervalued. Several key resources from the predictive workstreams have requested transfers, citing lack of engagement. Executive stakeholders are questioning whether the hybrid approach is sustainable. What is the MOST effective way to address this disparity?
September 29, 2026
You are managing a hybrid project where the development team uses Scrum while the compliance and regulatory workstreams follow a predictive approach. During sprint planning, a senior compliance officer insists on attending all Scrum ceremonies and has been providing detailed instructions to developers, effectively bypassing the Product Owner. Team velocity has dropped 30% over two sprints, and developers privately express frustration about conflicting priorities. The compliance officer believes their involvement is necessary due to regulatory risks. How should you address this situation?
September 29, 2026
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
September 24, 2026
Your manufacturing project has a budget of $500,000 and is scheduled to last 10 months. You are currently at the end of month 4. According to the project management plan, you should have spent $200,000 by now, but you have actually spent $180,000. The value of the work completed is $190,000. What is the Cost Variance (CV) for this project?
September 24, 2026
You are managing a government infrastructure project with strict documentation requirements. During a planning meeting, a stakeholder questions why you need to document lessons learned throughout the project rather than just at the end. The stakeholder is concerned about the additional administrative burden. What is the primary benefit of documenting lessons learned throughout the project lifecycle?
September 24, 2026
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
September 24, 2026
You are managing a construction project to build a new office facility. During project planning, you identify that concrete foundation work cannot begin until the excavation is complete and inspected. The concrete must cure for 7 days before framing can start. You need to document these relationships in your project schedule. What type of dependency exists between excavation and foundation work?
September 24, 2026
A project manager is leading a hybrid project to launch a new e-commerce platform. The infrastructure deployment follows a predictive approach, while feature development uses Scrum. During a retrospective, the Scrum team reports frustration that infrastructure dependencies are blocking their work. The infrastructure team says they are following their plan and cannot accommodate unplanned requests. What should the project manager do?
September 23, 2026
A healthcare organization is launching a hybrid project to develop a patient portal. The project includes predictive regulatory approval phases and adaptive feature development sprints. During a steering committee meeting, executives ask how the project will ensure compliance with healthcare privacy regulations while maintaining development speed. What is the best approach for the project manager to take?
September 23, 2026
A project manager is working on a hybrid project to modernize a legacy billing system. The organization has a strong compliance department that requires detailed documentation for audit purposes. The adaptive team members express concern that creating comprehensive documentation conflicts with agile principles. What should the project manager do to balance these competing demands?
September 23, 2026
An organization is implementing a hybrid approach for a product development project. The hardware components will follow a predictive waterfall methodology due to manufacturing constraints, while the software components will use Scrum for flexibility. A team member from the hardware team asks why the software team has daily standups while the hardware team has weekly status meetings. How should the project manager respond?
September 23, 2026
A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?
September 23, 2026
You are managing a marketing campaign project using a hybrid approach where creative content is developed iteratively with weekly reviews, while media buying and contracts follow a predictive schedule with fixed commitments. Three weeks before launch, the iterative creative reviews reveal that the campaign messaging needs significant changes based on stakeholder feedback. However, media placements worth $200,000 have already been contracted based on the original creative concept, and changing them would incur 25% cancellation fees. The CMO insists the new messaging is essential for campaign success. How should you proceed?
September 22, 2026
Your hybrid project uses iterative development for software components and predictive planning for regulatory submissions. During a retrospective, the development team reports that 40% of their completed work from the last two sprints cannot be deployed because regulatory documentation hasn't kept pace with development velocity. The regulatory specialist, who works part-time on your project, states she can only document work after it's fully tested and stabilized. This creates a growing backlog of undocumented, undeployable features. What should you address first?
September 22, 2026
You are leading a hybrid project where software features are developed using Scrum while hardware components follow a stage-gate process. During a sprint review, the software team demonstrates a new feature that requires a hardware modification the hardware team didn't anticipate. The hardware team's next gate review isn't scheduled for six weeks, and making changes outside the stage-gate process violates organizational governance. The software feature cannot be released without the hardware change. What is the best way to handle this situation?
September 22, 2026
Your organization is implementing a new customer portal using a hybrid approach. The infrastructure and security components follow a predictive lifecycle with a fixed release date in six months, while the user interface features are being developed iteratively in two-week sprints. The product owner wants to release features to users as soon as they're ready, but the infrastructure team insists nothing can go live until the full security framework is complete. Stakeholders are pressuring you to show early value. How should you proceed?
September 22, 2026
You are managing a hybrid project where the product development team works in two-week sprints while the regulatory compliance team follows a waterfall approach with predefined milestones. During sprint planning, the development team commits to features that require compliance documentation, but the compliance team indicates they need four weeks' advance notice to complete their reviews. This misalignment has caused delays in three consecutive sprints. What should you do to address this integration challenge?
September 22, 2026
