PMP Practice Question: Process — Hybrid, Medium

Your hybrid project delivers software features iteratively while following a predictive schedule for regulatory compliance milestones. You're three months into the six-month project when a new competitor launches a product with features your stakeholders now want to prioritize. The product owner wants to immediately reprioritize the backlog to include these competitive features, but doing so would likely cause the team to miss a regulatory filing deadline scheduled for next month. The regulatory work cannot be delayed without significant business consequences. What should be your next step?