ProcessHybridMediumECO: Process Task 7.2

PMP Practice Question: ProcessHybrid, Medium

You're managing a marketing campaign project using a hybrid approach where creative development is agile and media buying follows predictive contracts. During a retrospective, the creative team expresses frustration that their iterative work is often wasted because media placements are locked in months ahead based on initial concepts. The media team counters that they need creative specifications early to negotiate the best rates and placements. This tension is affecting team morale and collaboration. What is the most effective way to address this underlying conflict?