PMP Practice Question: Business Environment — Predictive, Hard
A financial services company is executing a core banking system replacement project using a predictive methodology with a 30-month timeline and $95M budget. The project has completed detailed requirements, design, and procurement phases. During the development phase (month 16), the company acquires a smaller competitor that uses a different technology platform. The merger integration team proposes consolidating onto a single platform, which would either require abandoning the current project (wasting $42M invested) or forcing the acquired bank to migrate twice—first to their interim platform, then to the new system within 18 months. The PMO director asks the project manager to evaluate strategic options. Regulatory requirements mandate system consolidation within 24 months of acquisition closing. What analysis should the project manager prioritize?
Study this topic
- 📖Business Case Development and Project Justification
Master business case development for PMP success. Learn how to justify projects, align with strategy, and demonstrate value delivery to stakeholders.
- 📖What Should a Project Manager Do First? PMP Priority Logic
Master the 'do first' and 'do next' priority logic that appears throughout PMP exam questions. Learn frameworks to confidently choose the correct sequence every time.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More Business Environment Questions
View all →A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?
A project manager is working on a hybrid project to modernize a legacy billing system. The organization has a strong compliance department that requires detailed documentation for audit purposes. The adaptive team members express concern that creating comprehensive documentation conflicts with agile principles. What should the project manager do to balance these competing demands?
A project manager is leading a hybrid project to launch a new e-commerce platform. The infrastructure deployment follows a predictive approach, while feature development uses Scrum. During a retrospective, the Scrum team reports frustration that infrastructure dependencies are blocking their work. The infrastructure team says they are following their plan and cannot accommodate unplanned requests. What should the project manager do?