PMP Practice Question: Business Environment — Predictive, Hard

A financial services company is executing a core banking system replacement project using a predictive methodology with a 30-month timeline and $95M budget. The project has completed detailed requirements, design, and procurement phases. During the development phase (month 16), the company acquires a smaller competitor that uses a different technology platform. The merger integration team proposes consolidating onto a single platform, which would either require abandoning the current project (wasting $42M invested) or forcing the acquired bank to migrate twice—first to their interim platform, then to the new system within 18 months. The PMO director asks the project manager to evaluate strategic options. Regulatory requirements mandate system consolidation within 24 months of acquisition closing. What analysis should the project manager prioritize?