ProcessHybridHardECO: Process Task 1.2

Your hybrid project uses time-boxed iterations for software development and a phase-gate approach for hardware components. During iteration review, the team demonstrates completed software features, but stakeholders from the hardware division express concern that integration testing cannot occur until their component passes the design gate in 6 weeks. The software features cannot be released independently and are accumulating as technical inventory. Velocity metrics show the team is productive, but no value is being delivered to customers. What is the most appropriate action?