ProcessHybridHardECO: Process Task 2.9

You are managing a hybrid project where regulatory compliance features are being developed using a predictive approach while customer-facing enhancements follow Scrum. During sprint planning, the development team identifies dependencies between a compliance module (scheduled for completion in 3 months per the WBS) and a user interface feature planned for the current sprint. The compliance module is on the critical path and any acceleration would require additional resources. The product owner insists the UI feature delivers significant customer value and should not be delayed. What should you do first?