PMP Practice Question: Business Environment — Hybrid, Hard

A retail organization is executing a hybrid supply chain optimization project. The warehouse automation component uses predictive delivery due to equipment procurement lead times and facility construction requirements, while demand forecasting and inventory algorithms are developed iteratively using two-week sprints. The CFO announces that due to an unexpected acquisition, capital budgets are frozen for 90 days, affecting the warehouse automation procurement. However, the acquisition brings three distribution centers that could benefit from the inventory algorithms if adapted to their legacy systems. The agile team has capacity, but pivoting to legacy system integration wasn't in the original business case. The warehouse construction is 30% complete and cannot pause without contractor penalties. What should the project manager recommend?