PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 2.6

PMP Practice Question: ProcessPredictive, Medium

You are managing an infrastructure project with a fixed budget of $2.5 million. At the end of month 4, your earned value analysis shows: PV = $800,000, EV = $750,000, AC = $825,000. The project is planned for 12 months total. Based on this information, senior management asks you to forecast the final project cost. What is the most appropriate estimate at completion (EAC) to present if you expect current performance to continue?

← All questions
📖

Study this topic

WBS Work Breakdown Structure: Proven Best Practices

Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi

More Process Questions

View all →
PMP Practice Question — Process · Medium | PMP Guide