PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 2.6

PMP Practice Question: Process — Predictive, Medium

You are managing an infrastructure project with a fixed budget of $2.5 million. At the end of month 4, your earned value analysis shows: PV = $800,000, EV = $750,000, AC = $825,000. The project is planned for 12 months total. Based on this information, senior management asks you to forecast the final project cost. What is the most appropriate estimate at completion (EAC) to present if you expect current performance to continue?

← All questions

Study this topic