You are managing a complex engineering project with 47 identified risks in your risk register. During a risk audit, your PMO director challenges your risk response strategy for Risk #23, which has a probability of 35% and an impact of $180,000 if it occurs. You have allocated $45,000 from the contingency reserve to implement a mitigation strategy that will reduce the probability to 15% and the impact to $120,000. The mitigation work will take 3 weeks and consume resources from the critical path. The PMO director argues that this mitigation strategy is not cost-effective. What is the most valid justification for your mitigation approach?
Study this topic
WBS Work Breakdown Structure: Proven Best PracticesMaster the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi…
More Process Questions
View all →You are leading an agile project to develop a mobile banking application. The team has just completed Sprint Planning and committed to delivering eight user stories in the upcoming two-week sprint. During the daily standup on day three, a developer mentions that one of the stories is taking much longer than estimated and may not be completed. What should you do first?
During a sprint retrospective for your software development project, team members identify that unclear user story acceptance criteria have caused significant rework in the past three sprints. The team estimates that 30% of their time has been spent redoing work that didn't meet unstated expectations. What should the team do to address this issue?
Your agile team is building an e-commerce platform. At the sprint review, the team demonstrates a completed shopping cart feature to stakeholders. The functionality works as specified in the user story, but the product owner notices the user interface colors don't match the company's recently updated brand guidelines, which changed during the sprint. What should happen next?