PMP Guide — Empowering Project Managers
ProcessPredictiveHardECO: Process Task 6.2

PMP Practice Question: Process — Predictive, Hard

You are managing a complex engineering project with 47 identified risks in your risk register. During a risk audit, your PMO director challenges your risk response strategy for Risk #23, which has a probability of 35% and an impact of $180,000 if it occurs. You have allocated $45,000 from the contingency reserve to implement a mitigation strategy that will reduce the probability to 15% and the impact to $120,000. The mitigation work will take 3 weeks and consume resources from the critical path. The PMO director argues that this mitigation strategy is not cost-effective. What is the most valid justification for your mitigation approach?

← All questions

Study this topic