PMP Practice Question: Process — Agile, Medium
You are leading a Scrum team developing a customer relationship management (CRM) system. During sprint planning, the product owner presents a high-priority user story estimated at 21 story points, which exceeds the team's average velocity of 35 points per two-week sprint. The product owner insists this feature is critical for an upcoming sales conference in three weeks and must be completed in the next sprint. Several team members suggest breaking down the story, but the product owner argues that all components must be delivered together to be valuable. How should you proceed?
Study this topic
- 📖Agile Sprint Planning Techniques for the 2026 PMP Exam
Master sprint planning techniques essential for the 2026 PMP exam. Learn how to apply timeboxing, capacity planning, and story estimation in hybrid environments.
- 📖EVM TCPI Trap: Why Schedule Variance Is Zero at Project End
Understanding why schedule variance drops to zero at project completion is critical for EVM mastery. Learn the TCPI trap and how to avoid misinterpreting earned value metrics on the PMP exam.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
