Your organization is implementing a new customer relationship management (CRM) system using a hybrid approach. The core infrastructure deployment follows a predictive waterfall methodology with detailed planning, while feature development uses two-week sprints. A major competitor has just announced a similar product launch in four months, pressuring executive leadership to accelerate delivery. The CFO requests that you compress the infrastructure phase from six months to three months to enable earlier feature releases. What should you do first?