PMP Practice Question: Business Environment — Predictive, Medium

A project manager is leading a predictive ERP implementation project for a financial services company. During execution, a major cybersecurity breach occurs at a competitor, resulting in significant regulatory scrutiny across the industry. The regulatory body issues new data security requirements that affect how customer information must be encrypted and stored. These requirements were not part of the original project scope or compliance assessment. The changes would add 2 months and $500,000 to the project. What is the most appropriate course of action?