PMP Practice Question: Business Environment — Predictive, Medium

A project manager is overseeing a twelve-month software implementation project using a waterfall approach for a financial services client. After six months of development, a major competitor launches a similar product with additional features that are generating significant market interest. The client's executive team is concerned about competitive positioning and asks the project manager to incorporate similar features into the current project. The project is currently on schedule and within budget. How should the project manager respond?