PMP Practice Question: Business Environment — Predictive, Medium

A project manager is leading a predictive project to develop a new medical device. During the planning phase, the sponsor informs the project manager that a competitor has just announced a similar product launch in 12 months. The original project schedule was 18 months, with significant regulatory approval milestones at months 6, 12, and 15. The sponsor wants to know if the project can be accelerated to match the competitor's timeline without compromising regulatory compliance. What should the project manager do first?