PMP Practice Question: Business Environment — Hybrid, Hard

Your hybrid project is developing a manufacturing execution system for a global company. The predictive track covers hardware installation across 12 facilities (using earned value management), while the adaptive track develops the software platform (5 teams using SAFe). During a portfolio review, the CFO announces that due to acquisition opportunities, capital expenditure approvals will now require portfolio committee review with 4-week lead time, and all projects must demonstrate ROI within 24 months instead of 36. Your hardware installations are performing well (SPI 1.05, CPI 0.98), but the software teams have been building foundation layers with limited visible functionality. The product owner has been deferring user-facing features to later program increments. What should you do FIRST to address the new portfolio constraints?