A pharmaceutical company is executing a hybrid project to develop a new drug delivery system. The predictive regulatory approval track has completed its gate review, while the agile development team is in Sprint 8 of 12. A competitor announces FDA approval of a similar product that will reach market in 6 months. The executive sponsor requests immediate portfolio rebalancing to accelerate time-to-market. Market analysis shows that being second-to-market reduces projected ROI from 32% to 14%, but rushing development could compromise quality gates required for regulatory compliance. What should the project manager do first?