PMP Practice Question: Business Environment — Hybrid, Hard

A healthcare technology project is implementing an electronic health records system using a hybrid approach: core clinical database using predictive methodology, and user interface modules using Scrum. Six months into the 18-month project, a competitor launches a superior product with AI-powered diagnostic suggestions. The executive sponsor wants to pivot and add AI capabilities to remain competitive, estimating this will require 40% of the remaining budget and extend the timeline by 4 months. Market analysis shows the competitive threat is real, but the hospital network has committed to the original go-live date for operational reasons. The CFO is unwilling to increase the budget. How should the project manager address this situation?