You are managing a multi-year government infrastructure project using a predictive approach. Six months into execution, a key technical lead who has been with the project since initiation submits their resignation, citing a better opportunity elsewhere. This individual possesses critical knowledge about design decisions and has established relationships with several government stakeholders. Their departure is scheduled for three weeks from now. The project is currently on track, but several complex deliverables are planned for the next quarter. What is your best course of action?