Business EnvironmentHybridMediumECO: Business Environment Task 1.3

PMP Practice Question: Business Environment — Hybrid, Medium

A manufacturing company is implementing a new ERP system using a hybrid approach. The core system configuration follows a predictive schedule, while business process redesign uses iterative sprints. Six months into the eighteen-month project, a major competitor announces bankruptcy, creating an unexpected opportunity for the company to acquire market share. Executive leadership wants to accelerate the project completion by four months to capitalize on this market opportunity. The project manager assesses that compressing the predictive infrastructure work carries high technical risk. What is the BEST approach to respond to this business opportunity?