PMP Practice Question: Business Environment — Predictive, Medium

A project manager is leading a government infrastructure project using a predictive approach. A new regulation is passed requiring all public infrastructure projects to conduct additional environmental impact assessments that were not part of the original compliance requirements. The regulation becomes effective immediately and applies to all ongoing projects. The project team has already completed the design phase, and procurement activities are underway. What is the most appropriate action?