PMP Practice Question: Business Environment — Predictive, Hard

A pharmaceutical company is executing a predictive project to build a new manufacturing facility. The project is 40% complete when a competitor announces a breakthrough technology that could make the planned facility's production method obsolete within 3-5 years instead of the projected 15-year lifecycle. The project has already spent $45M of a $120M budget. Market analysts predict the competitive landscape will shift significantly, but there is uncertainty about regulatory approval timelines for the new technology. The project sponsor wants to continue as planned, citing sunk costs and the need for near-term production capacity. Senior executives are divided. What is the MOST appropriate action for the project manager?