PMP Practice Question: Business Environment — Predictive, Medium

A project manager is leading a predictive infrastructure project for a utility company. During project planning, the finance department informs the project manager that the organization is transitioning to a new enterprise resource planning (ERP) system in three months, which will change all financial reporting and procurement processes. The project has a 12-month duration and requires significant procurement activities throughout execution. What should the project manager do to address this organizational change?