PMP Practice Question: Business Environment — Hybrid, Medium

A pharmaceutical company is executing a hybrid project to develop a new drug delivery system. The predictive regulatory approval phase runs parallel to agile development sprints for the mobile app interface. A new government regulation requires additional clinical trial documentation, impacting both workstreams. The project manager has identified that the regulatory team needs 3 additional months while the development team can adapt within their sprint cycle. What should the project manager do first?