A project manager is leading a predictive software development project for a financial services client. The project team has identified an opportunity to implement a new technology that would significantly reduce operational costs for the client after project completion. However, adopting this technology would require additional development time and increase the project budget by 15%. The current project is meeting all baseline requirements, and the client has not requested this enhancement. What should the project manager do?