PMP Practice Question: Business Environment — Predictive, Hard

Your organization has recently merged with a competitor, creating significant shifts in strategic priorities. The PMO director has asked you to reassess your ongoing predictive infrastructure project, which is 40% complete and on schedule. The merged entity's new strategic plan emphasizes cloud-based solutions, while your project is implementing on-premise data centers. Senior leadership is divided—some want to continue as planned to avoid sunk costs, while others advocate for immediate termination. The project has already consumed $2.4M of a $6M budget and has binding contracts with hardware vendors totaling $1.8M. What should you do first?