You are leading a predictive software development project for a financial institution. A key developer who is responsible for the security module has been consistently missing deadlines over the past three weeks. This developer was previously a high performer. During a one-on-one conversation, you learn that they are dealing with a personal family situation that requires significant attention. The security module is on the critical path, and any further delays will impact the project delivery date committed to the sponsor. What is the most appropriate course of action?