PMP Practice Question: Business Environment — Predictive, Easy
A project manager is leading a government infrastructure project with a fixed contract of $5 million and a timeline of 18 months. Three months into the project, new environmental regulations are passed that will require additional permitting and compliance documentation. The sponsor asks the project manager how this will affect the project. What should the project manager do first?
Study this topic
- 📖Change Management Across Agile and Predictive Approaches
Master how change management differs between agile and predictive project approaches for the PMP exam. Learn practical techniques for handling change in hybrid environments.
- 📖Change Management in Predictive vs Agile Projects
Discover how change management differs between predictive and agile approaches, and master the flexible strategies needed for the 2026 PMP exam's 60% Agile focus.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More Business Environment Questions
View all →A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?
A project manager is working on a hybrid project to modernize a legacy billing system. The organization has a strong compliance department that requires detailed documentation for audit purposes. The adaptive team members express concern that creating comprehensive documentation conflicts with agile principles. What should the project manager do to balance these competing demands?
A project manager is leading a hybrid project to launch a new e-commerce platform. The infrastructure deployment follows a predictive approach, while feature development uses Scrum. During a retrospective, the Scrum team reports frustration that infrastructure dependencies are blocking their work. The infrastructure team says they are following their plan and cannot accommodate unplanned requests. What should the project manager do?
