PMP Practice Question: Business Environment — Hybrid, Hard

A healthcare organization is executing a hybrid EHR integration project across 12 hospitals. The core platform migration follows a predictive rollout schedule, while individual hospital customizations use iterative sprints. During Sprint 6 at Hospital C, clinicians report that the agile-developed workflow optimizations conflict with newly announced federal interoperability regulations taking effect in 8 months. Compliance requires specific data exchange standards not in the current architecture. The predictive platform vendor indicates that regulatory compliance features won't be available until the next major release in 14 months. Hospitals D through L haven't started their customization sprints yet. What is the most appropriate response?