PMP Practice Question: Business Environment — Hybrid, Medium

A telecommunications company is deploying a network infrastructure upgrade using a hybrid approach. The physical infrastructure deployment follows a predictive schedule across 50 cities, while the software-defined networking features are developed using Scrum. Three months into the project, a major technology vendor announces end-of-life for a key hardware component that was planned for 30 of the remaining cities. The vendor is offering a next-generation replacement that provides better performance but requires different configuration and has a longer lead time. How should the project manager address this market change?