PMP Practice Question: Business Environment — Hybrid, Hard

You are managing a hybrid project to develop a new financial services platform. The core architecture (predictive, 9-month timeline) must meet strict regulatory compliance requirements, while customer-facing features are being developed iteratively. During a compliance audit, regulators identify a new requirement that necessitates significant architectural changes. Your architecture team estimates 4 months of additional work, which would delay the predictive track and block all adaptive sprints that depend on the platform. The product owner wants to continue adaptive development on other features, but the architecture team insists everything must pause. How should you proceed?