A project manager is executing a government contract project using a predictive approach. The project has strict compliance requirements and formal change control processes. A new technology solution becomes available that could reduce project costs by 15% and improve the final product's performance. However, implementing this technology would require significant design changes and extend the schedule by two months. The contract includes performance incentives for early completion. What should the project manager evaluate first when considering this opportunity?