PMP Practice Question: Business Environment — Predictive, Medium

You are managing a predictive government infrastructure project with a 24-month timeline and fixed budget. Six months into execution, a new environmental regulation is enacted that requires additional environmental impact assessments for all projects in your sector. The regulation will add 3 months to your schedule and increase costs by 15%. Your sponsor is concerned about the project's viability. What should you do first?