PMP Practice Question: Business Environment — Predictive, Hard

You are managing a predictive government defense project under a firm-fixed-price contract. Six months into the 18-month effort, a new federal regulation is published that requires significant changes to data encryption standards for all systems handling classified information. Your project was 95% compliant with the old standards, but the new regulation requires hardware replacements and software re-engineering affecting 40% of completed work. The contracting officer has confirmed this constitutes a changes in law provision under the contract. Your executive sponsor is pressuring you to absorb the changes within the existing budget to preserve the company's reputation with this client. What is the MOST appropriate course of action?