Your organization is implementing a hybrid project to digitally transform its supply chain operations across three regions. During sprint planning, the CFO informs you that due to an unexpected market downturn, the project budget will be reduced by 30% starting next quarter. The predictive portion involves legacy system integration (60% complete), while the adaptive portion focuses on developing a customer-facing mobile application (3 sprints completed of 8 planned). Several vendors have already been contracted for the predictive work, and two agile teams are fully staffed. What should be your FIRST action to address this budget constraint?