PMP Practice Question: Business Environment — Hybrid, Medium

A healthcare organization is executing a hybrid project to modernize its patient record system. Regulatory compliance requirements are managed predictively with detailed documentation and gate reviews, while user experience enhancements follow an adaptive approach with two-week sprints. Midway through the project, a new healthcare privacy regulation is enacted that requires additional data encryption and audit logging capabilities. The compliance team estimates this will require four months of additional work in the predictive track. The project is currently on schedule to meet a regulatory deadline for the old requirements in six months. How should the project manager address this external compliance change?