You are leading an agile project team that has been working together for three iterations. During the last retrospective, team members expressed frustration about not understanding the business value of the user stories they are working on. The product owner has been unavailable due to other commitments. Team velocity has started to decline, and members seem less engaged during daily standups. What should you do first to address this situation?