PMP Guide — Empowering Project Managers
Business EnvironmentPredictiveHardECO: Business Environment Task 1.4

PMP Practice Question: Business Environment — Predictive, Hard

A project manager is overseeing a large construction project using a predictive approach when the organization announces a major merger with a competitor. The merger brings significant organizational changes including new executives, revised strategic priorities, and potential consolidation of project portfolios. The project is 55% complete and on track to deliver within baseline constraints. However, three weeks after the merger announcement, the project manager learns informally that a similar project exists in the acquired company and both projects may be evaluated for continuation. The formal portfolio review is scheduled for 8 weeks away. The project team is concerned about job security, and two key resources have started interviewing elsewhere. What should the project manager do?

← All questions

Study this topic