PMP Practice Question: Business Environment — Agile, Medium

A financial services company is running an agile project to modernize their loan processing system. During a retrospective, the compliance officer raises concerns that the team's rapid iteration cycles don't allow sufficient time for regulatory review before features go to production. The team has been deploying to production every two weeks, but the compliance review process typically takes three weeks. This has caused several production deployments to be rolled back due to compliance issues. How should the project manager address this situation?