Your agile team is developing a mobile healthcare application in a regulated environment. During sprint planning for sprint 8, the product owner presents user stories for a new patient data-sharing feature. The team identifies that implementing this feature requires integrating with a legacy hospital system that has unreliable APIs and poor documentation. Past experience shows that such integrations typically reveal unknown dependencies mid-sprint. The product owner insists this feature is critical for a partnership announcement in four sprints and must begin now. The team is concerned about committing to a sprint goal they may not achieve. What approach best balances the business urgency with empirical process control?