Your hybrid project has a co-located agile development team and distributed subject matter experts who provide input for the predictive requirements phase. You notice that the distributed SMEs rarely participate in collaborative sessions, often sending delegates who lack decision-making authority. This has caused a three-week delay in finalizing critical architectural decisions. When you discuss this with the SMEs, they explain they're already overcommitted to operational duties and cannot justify more time away. The project is behind schedule, and stakeholders are pressuring you to accelerate delivery. How should you handle this situation?