PMP Practice Question: Business Environment — Agile, Medium
Your agile team is developing a mobile banking application when a new government regulation is announced requiring two-factor authentication for all financial transactions within 90 days. The current sprint backlog does not include this functionality, and the product owner is concerned about compliance. The team has three sprints remaining before the original release date. What should the product owner do first?
Study this topic
- 📖Change Management in Predictive vs Agile Projects
Discover how change management differs between predictive and agile approaches, and master the flexible strategies needed for the 2026 PMP exam's 60% Agile focus.
- 📖Scope Management: Defining and Controlling What Your Project Delivers
Master scope management techniques that prevent scope creep, ensure stakeholder alignment, and deliver exactly what your project commits to achieve.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Business Environment Questions
View all →A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?
A project manager is working on a hybrid project to modernize a legacy billing system. The organization has a strong compliance department that requires detailed documentation for audit purposes. The adaptive team members express concern that creating comprehensive documentation conflicts with agile principles. What should the project manager do to balance these competing demands?
A project manager is leading a hybrid project to launch a new e-commerce platform. The infrastructure deployment follows a predictive approach, while feature development uses Scrum. During a retrospective, the Scrum team reports frustration that infrastructure dependencies are blocking their work. The infrastructure team says they are following their plan and cannot accommodate unplanned requests. What should the project manager do?