PMP Practice Question: ProcessPredictive, Medium

Your manufacturing project is in the execution phase. A critical supplier informs you that a key component will be delayed by three weeks due to material shortages. This component is on the critical path and was scheduled to be delivered in two weeks. You review your risk register and find that supplier delays were identified as a risk, with a mitigation strategy to identify alternate suppliers. However, no alternate suppliers were pre-qualified. What should you do first?