During a sprint retrospective, a senior developer consistently dominates the conversation, speaking for 80% of the meeting time. Several junior team members have stopped participating and appear disengaged. The Scrum Master notices this pattern has occurred in the last three retrospectives. The team's velocity has been declining, and post-retrospective surveys show decreased satisfaction among junior members. What should the Scrum Master do to address this situation?