PMP Practice Question: Process — Predictive, Medium

Your manufacturing project is in the planning phase, and you are developing the cost baseline. You have completed bottom-up estimating for all work packages and have aggregated these costs. The finance department requires a 10% management reserve for organizational risks, and historical data shows similar projects typically experience 15% cost variance. Your project sponsor asks what the final project budget should include. What is the MOST appropriate approach?