Your pharmaceutical project is developing a new drug formulation with strict FDA validation requirements. The project is using a stage-gate approach with formal quality reviews at each phase. During the Phase 2 gate review, quality auditors identify that 12 of 47 deliverables from Phase 1 do not fully meet the documented acceptance criteria, though they passed initial reviews. Reworking these deliverables will cost $340,000 and delay the project by 6 weeks. The Phase 1 project manager, who has since left the company, approved these deliverables based on verbal agreements with stakeholders that differ from the documented requirements. What should you do FIRST?