You are managing a hybrid project where the development team follows Scrum while the infrastructure team uses a waterfall approach. During a retrospective, several developers express frustration that infrastructure delays are blocking their sprint goals. The infrastructure lead explains their team must follow a strict change control process that takes 2-3 weeks for approvals. Team morale is declining as developers feel their efforts are wasted. What should you do first to address this conflict?