PMP Practice Question: Business Environment — Hybrid, Hard

A financial services company is implementing a regulatory compliance system using a hybrid approach. The predictive-planned infrastructure component is on track, but the iterative customer-facing interface has fallen behind due to changing regulatory interpretations. The compliance deadline is fixed by law and cannot be moved. Senior leadership is pressuring the project manager to cut scope from the agile component to meet the deadline. However, the product owner insists that all planned features are minimum viable requirements for regulatory acceptance. What should the project manager do first?