Business EnvironmentHybridMediumECO: Business Environment Task 1.2

PMP Practice Question: Business Environment — Hybrid, Medium

A financial services company is developing a customer portal using a hybrid delivery approach. The security and compliance components follow predictive planning due to regulatory requirements, while the user experience features are developed iteratively based on customer feedback. During a sprint review, the compliance officer raises concerns that new data privacy regulations will take effect in six months, potentially requiring significant changes to the security architecture already under development. The project is currently 40% complete. What is the most appropriate response?