PMP Practice Question: Business Environment — Predictive, Hard

A construction project manager is overseeing a government infrastructure project using earned value management. At month 18 of a 30-month project, the metrics show: PV=$45M, EV=$38M, AC=$42M, BAC=$75M. A new administration has taken office and announced a comprehensive review of all capital projects, with emphasis on cost efficiency and transparency. The project has strategic importance for regional economic development but faces public criticism over cost overruns. The project sponsor asks the project manager to present options to the newly formed oversight committee. Which recommendation should the project manager present as PRIMARY priority?