PeoplePredictiveHardECO: People Task 3.1

PMP Practice Question: PeoplePredictive, Hard

You are leading a construction project that is 60% complete. During a routine team performance assessment, you discover that your site supervisor has been consistently inflating progress reports to make their team appear more productive. Upon investigation, you learn the supervisor was responding to intense pressure from the construction manager to meet aggressive milestones, and feared their team would be viewed negatively. The actual progress indicates the project is approximately 3 weeks behind schedule. The construction manager is unaware of the misreported data and is making decisions based on the inflated reports. What should you do?

← All questions
📖

Study this topic

Will AI Replace Project Managers? The Honest Answer

Explore the realistic impact of AI on project management careers, what the 2026 PMP exam teaches about AI integration, a

More People Questions

View all →
1
MediumAgile

During sprint planning, your development team commits to 45 story points based on historical velocity. However, your product owner insists they must complete 60 story points this sprint because of a commitment made to a key stakeholder. The product owner argues that the team 'just needs to work harder' and threatens to escalate to senior management if the team doesn't comply. The team looks to you, the Scrum Master, for guidance. How should you respond?

2
MediumAgile

Your agile team has a new member, Sarah, who joined two weeks ago. Sarah has strong technical skills but comes from a traditional waterfall background. During the current sprint, you notice Sarah working in isolation, not updating the task board, and not asking for help despite her story being blocked. In the standup, she reports 'everything is fine' even though you can see she's struggling. Other team members have offered help, but she politely declines. What is the most effective way to help Sarah adapt to the agile team environment?

3
MediumAgile

Your agile team has been consistently meeting sprint commitments, but during a recent retrospective, team members admitted they have been padding estimates significantly to ensure they never miss a commitment. The team's capacity allows them to complete stories early, but they wait until late in the sprint to pull in additional work to avoid looking like they overcommitted. The product owner is frustrated because the team could be delivering more value. What should you do to address this behavior?